Mineral Economics, Mine Planning, Systems Engineering · Mine Planning · 2 marks · Multiple choice
Match semivariogram shapes P–S with models I pure nugget, II exponential, III spherical, IV Gaussian, and properties E reaches sill at finite range, F reaches sill asymptotically, G reaches sill instantaneously. Retain the printed option combinations.
P has the spherical shape with a finite-range sill (III, E). Q is exponential and approaches its sill asymptotically (II, F). R has the smooth near-origin Gaussian shape (IV). S is pure nugget, reaching its nonzero sill immediately for positive lag (I, G). These model identities select A. Source caveat: A prints property E for the Gaussian model, although an exact Gaussian variogram approaches its sill asymptotically; only a practical-range approximation treats it as having reached the sill.
More Mine Planning questions
GATE 2022 MN Q63– A 12 m thick coal seam dips 30°, has density 1.41 tonne/m³ and is mined with a 45° pit…
GATE 2021 MN Q63– Ultimate-pit cumulative million tonnes below Cu grades 0.1%, 0.4%, 0.5%, 0.6%, 0.7%, 0.9%+…
GATE 2026 MN Q46– The exploratory boreholes and their influence polygons are shown. With equal density…