GATE 2025 AR — Planning – Question 21
Choose the normal sequence of architectural drawings through design and construction.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (C) Concept → Statutory approval → Working → Completion
Explanation
Concept drawings establish the proposal, approval drawings secure statutory permission, working drawings communicate construction details, and completion drawings record the finished work. This gives C. Although real projects involve iterations, the sequence of these named stages is as listed.