GATE 2025 AR — Planning – Question 21

Project Management and Professional Practice · Professional practice and ethics · 1 mark · Multiple choice

Choose the normal sequence of architectural drawings through design and construction.

  1. Working → Approval → Concept → Completion
  2. Approval → Concept → Completion → Working
  3. Concept → Statutory approval → Working → Completion
  4. Concept → Working → Completion → Approval

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (C) Concept → Statutory approval → Working → Completion

Explanation

Concept drawings establish the proposal, approval drawings secure statutory permission, working drawings communicate construction details, and completion drawings record the finished work. This gives C. Although real projects involve iterations, the sequence of these named stages is as listed.