GATE 2021 AR – Question 35
Order the contract activities P bid opening, Q security-deposit submission, R Notice Inviting Tender publication, S Letter of Intent issue, T Earnest Money Deposit submission.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (C) R–T–P–S–Q
Explanation
Publish the tender notice, receive the bid with EMD, open/evaluate bids, issue the letter of intent, then obtain the post-award security deposit. The source sequence is R–T–P–S–Q, C. Bid security and the successful contractor’s security deposit occur at different stages.