GATE 2020 AR – Question 53

Infrastructure, Services and Utilities · Stormwater drainage and management · 2 marks · Numerical answer

In a residential complex, the central play area is to be converted into a detention pond for stormwater management. For a 24-hour rainfall event of 100 mm, 100% of stormwater from the central play area and 70% of stormwater runoff from the rest of the complex is to be held at the detention pond. The required pond depth (in mm) is _____.

Surface typeArea (m$^2$)Runoff coefficient
Apartment blocks12500.80
Central play area1500.60
Other permeable areas2000.70
Other impermeable areas4000.90

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 760 to 760

Explanation

We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort