GATE 2020 AR – Question 56

Planning Policy and Practice · Project planning and management · 2 marks · Numerical answer

The activity duration, early start, early finish, late start and late finish of activities P, Q and R are shown in the figure. The independent float of activity Q is _____.

Diagram for GATE 2020 AR question 56

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 1 to 1

Explanation