GATE 2020 AR – Question 56
The activity duration, early start, early finish, late start and late finish of activities P, Q and R are shown in the figure. The independent float of activity Q is _____.

Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 1 to 1
Explanation
We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort