GATE 2018 AR – Question 4

Project Management and Professional Practice · 1 mark · Multiple choice

In Critical Path Method (CPM) for time scheduling, ‘forward pass calculation’ is carried
out for determining

  1. Late start and early finish time
  2. Early start and early finish time
  3. Late start and late finish time
  4. Early start and late finish time

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) Early start and early finish time

Explanation