GATE 2018 AR – Question 48

Design and Graphics · 2 marks · Numerical answer

For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days
and ‘most-likely time duration’ is 8 days. The PERT value of time duration is______ days
(up to one decimal place).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 7.8 to7.9

Explanation