GATE 2018 AR – Question 48
For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days
and ‘most-likely time duration’ is 8 days. The PERT value of time duration is______ days
(up to one decimal place).
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 7.8 to7.9
Explanation
We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort