GATE 2018 PI – Question 23

Engineering Mathematics · 1 mark · Numerical answer

Processing times on a single machine for 3 jobs are given below. All the jobs are available
at time t = 0.

Job
1
2 3
Processing time (minute) 15 3 6

The mean flow time (in minute) as per the shortest processing time (SPT) sequence
is _______

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 11.8 to 12.2

Explanation