GATE 2018 PI – Question 32

Industrial Engineering · 2 marks · Multiple choice

Actual and forecasted demands of a product are as follows:

Period
1
2
3
4
5
Actual demand
180 170 165 170 200
Forecasted demand 190 190 190 190 190

The forecast error measured in terms of mean absolute deviation (MAD) and mean absolute
percentage error (MAPE), respectively, are

  1. 13 and 7.84%
  2. 13 and 9.85%
  3. 17 and 7.84%
  4. 17 and 9.85%

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (D) 17 and 9.85%

Explanation