GATE 2018 PI – Question 43

Engineering Mathematics · 2 marks · Numerical answer

A project consists of three activities P, Q and R. The durations of activities follow Beta
distribution. The predecessors and durations of activities are as per the following table:

Activity
Predecessors
Optimistic time
(month)
Most likely time
(month)
Pessimistic time
(month)
P
—
2
3
10
Q
P
3
5
13
R
Q
3
4
5

The expected project completion time (in month) is ______

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 13.9 to 14.1

Explanation