GATE 2018 PI – Question 43
A project consists of three activities P, Q and R. The durations of activities follow Beta
distribution. The predecessors and durations of activities are as per the following table:
Activity
Predecessors
Optimistic time
(month)
Most likely time
(month)
Pessimistic time
(month)
P
—
2
3
10
Q
P
3
5
13
R
Q
3
4
5
The expected project completion time (in month) is ______
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 13.9 to 14.1
Explanation
We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort