GATE 2024 XH-C6 (Sociology) – Question 8

General Aptitude · Quantitative Aptitude: Data Interpretation, Arithmetic and Number Computation · 2 marks · Multiple choice

The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).

The Capacity Factor of a power generation technology is:

$\text{Capacity Factor} = \frac{\text{Electricity Generation (MWh)}}{\text{Installed Capacity (MW)} \times 1000\ \text{(h)}}$

Which one of the given technologies has the highest Capacity Factor?

Bars (installed capacity, right axis in MW) and crosses (electricity generation, left axis in MWh) for T1 to T4. T1: bar at 20 MW, cross at 10000 MWh. T2: bar at 30 MW, cross at 9000 MWh. T3: bar at 15 MW, cross at 7000 MWh. T4: bar at 40 MW, cross at 12000 MWh.
  1. T1
  2. T2
  3. T3
  4. T4

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (A) T1

Explanation

Compare generation divided by installed capacity times 1,000 hours for each technology. The keyed maximum capacity factor is T1.