GATE 2024 CE (CE1) – Question 53

Geotechnical Engineering · Compaction and one-dimensional consolidation · 2 marks · Numerical answer

The total primary consolidation settlement ($S_c$) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of the building, primary consolidation settlement was reported as 10 mm. The additional time (in days) required to achieve 50% of $S_c$ will be ______________________ (rounded off to the nearest integer).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 1575

Explanation

After 300 days the degree of consolidation is $U = \frac{10}{50} = 20\%$. For $U < 60\%$ the time factor is $T_v = \frac{\pi}{4}U^2$, so $t \propto U^2$. The time for 50% is $t_{50} = 300 \times \left(\frac{0.5}{0.2}\right)^2 = 300 \times 6.25 = 1875$ days. The additional time is $1875 - 300 = 1575$ days.