GATE 2024 CE (CE2) – Question 17
Consider the statements P and Q.
P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.
Q: A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.
Which one of the following options is CORRECT?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (B) P is TRUE and Q is FALSE
Explanation
In a pure (projectized) organisation the project manager has full authority over the team and the resources, so P is true. A matrix organisation has dual reporting lines, which slows decisions and creates conflicts, so it does not give a quick response, and Q is false.