GATE 2024 CE (CE2) – Question 19
Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The 'schedule variance' for the project is
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) (−)Rs. 50
Explanation
In earned value analysis, the schedule variance is $SV = BCWP - BCWS = 150 - 200 = -\text{Rs. } 50$. It is expressed in money, and it is negative, so the project is behind schedule.