The GATE Grind

GATE 2023 CH – Question 63

Plant Design and Economics · Depreciation, rate of return, payback period and discounted cash flow · 2 marks · Numerical answer

A design engineer needs to purchase a membrane module (M) for a plant. Details about the two available options, M1 and M2, are given in the table below. The overall plant has an expected life of 7 years. If the interest rate is 8% per annum, compounded annually, the difference in the net present value (NPV) of these two options, in lakhs of rupees, is ______ (rounded off to one decimal place).

M1M2
Purchase cost (in lakhs of rupees)105
Expected life (years)53

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 4.68 to 4.72

Explanation

Over the plant life of 7 years, each module is replaced when its life ends. M1 is bought at year 0 and at year 5, so its present cost is $10 + \frac{10}{1.08^5} = 10 + 6.806 = 16.806$ lakhs. M2 is bought at years 0, 3 and 6: $5 + \frac{5}{1.08^3} + \frac{5}{1.08^6} = 5 + 3.969 + 3.151 = 12.120$ lakhs. The difference is $16.806 - 12.120 = 4.7$ lakhs.