GATE 2020 ME (ME2) – Question 8
52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men are sent to another project. How many days MORE than the original estimate will completion require?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) 3 days
Explanation
Total work is 52×10=520 man-days. With 40 men, time is 520/40=13 days. The question asks extra time over the original estimate, so **13−10=3 days, A**. This assumes unchanged individual productivity.