Correct answer: (A) Location; (B) Inventory; (C) Distribution
Explanation
Facility location, inventory placement/policy and distribution networks are supply-chain decisions. Machine scheduling is treated here as an internal shop-floor operations decision. The official classification selects **A,B,C**.
More Production Control questions
GATE 2024 PI Q64– An item uses classical EOQ. Ordering cost per order rises 20% and demand rate also rises…
GATE 2024 PI Q65– Jobs A,B,C,D,E are ready at t = 0 and take 9,6,4,5,8 days respectively on one machine.…