GATE Water and Waste Water Quality and Treatment: Water requirement, distribution system and drinking water treatment – Previous Year Questions

6 GATE previous year questions on Water requirement, distribution system and drinking water treatment (Water and Waste Water Quality and Treatment, Civil Engineering) with answers and explanations, from every paper.

6 questions worth 9 marks in all (3 1-mark, 3 2-mark). Asked between 2018 and 2025, so you can see how the topic has been tested over time.

  1. GATE 2018 CE (CE2) Q61 (2 marks, Numerical answer) – A water-treatment plant has 4 filters with filtration and backwashing rates 200 and 1000 m³/day/m². Backwashing takes 15 min/day, and maturation after…
  2. GATE 2018 CE (CE1) Q43 (2 marks, Multiple choice) – A rapid sand filter must produce 99 MLD potable water. Backwashing loss is 5%, filtration rate 6 m/h, and each bed has length/width 1.35 and width 5.2…
  3. GATE 2024 CE (CE1) Q61 (2 marks, Numerical answer) – A water treatment plant treats 25 MLD water with a natural alkalinity of 4.0 mg/L (as CaCO 3). It is estimated that, during coagulation of this water,…
  4. GATE 2025 CE (CE2) Q34 (1 mark, Numerical answer) – Free residual chlorine concentration in water was measured to be 2 mg/l (as Cl 2). The pH of water is 8.5. By using the chemical equation given below,…
  5. GATE 2025 CE (CE1) Q21 (1 mark, Multiple choice) – Fecal Coliform (FC) concentration in river water was measured as 10780 cfu/100 ml. The FC concentration after the conventional water treatment, but…