GATE 2022 MA – Question 57
Three companies C₁,C₂,C₃ bid for three jobs J₁,J₂,J₃, each company taking one job. Cost rows are C₁:(10,12,8),C₂:(9,15,10),C₃:(15,10,9). Find the minimum assignment cost.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 27 to 27
Explanation
Enumerate job permutations (123),(132),(213),(231),(312),(321) for the companies. Their totals are 34,30,30,37,27,38. The minimum assigns C₁→J₃,C₂→J₁,C₃→J₂, costing 8+9+10=**27**.