GATE 2020 CY – Question 8

General Aptitude · Quantitative Aptitude: Data Interpretation, Arithmetic and Number Computation · 2 marks · Multiple choice

52 men can complete a highway strip between cities P and Q in 10 days. An emergency transfers 12 men to another project. How many more days than originally estimated are needed?

  1. 3 days
  2. 5 days
  3. 10 days
  4. 13 days

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (A) 3 days

Explanation

Total work is 52×10 = 520 man-days. Remaining workforce is 40, so completion takes 520/40 = 13 days at unchanged productivity. The extra duration is 13−10 = 3 days, A, not the total 13 days.