The wearing course directly receives tyres and protects the structural base. Below the base, the subbase spreads loads and separates/drains the pavement above the prepared natural subgrade. Thus the correct descending order is wearing course, base, subbase, subgrade, A.
More Mining Machinery questions
GATE 2022 MN Q34– A friction-winder skip accelerates from rest to its steady speed in 15 s. Use the given…
GATE 2022 MN Q51– A battery locomotive pulls mine tubs of total mass 3 tonnes up a 1-in-20 gradient.…
GATE 2022 MN Q52– A pump lifts water of density 1020 kg/m³ at 250 m³/hour from 150 m depth. Pipe-friction…
GATE 2022 MN Q53– A dumper spends 3 min at loading and 1 min unloading. Stations are 4.5 km apart; loaded…
GATE 2022 MN Q55– A shearer cuts a 3 m seam with 0.7 m web at 12 m/min. AFC trough area is 0.4 m² with…
GATE 2021 MN Q11– A tricone roller bit is used with which drilling system?