GATE 2026 AR — Architecture – Question 52

Building Construction, Materials, and Structural Systems · Building construction techniques, methods and details: foundation, plinth, masonry, bonds, fenestrations, arches, scaffolding, formwork, timber/RCC/Steel frame construction, roof and roof covering · 1 mark · Multiple choice

When is foundation setting-out executed?

  1. After excavation
  2. After foundation concreting
  3. Before excavation
  4. Before placing plinth-beam reinforcement

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (C) Before excavation

Explanation

Setting-out transfers the designed axes, positions and dimensions to the site so excavation can be carried out in the correct locations. It therefore precedes foundation excavation, C. Later checks are also made, but they do not change the initial sequence asked here.

More Building construction techniques, methods and details: foundation, plinth, masonry, bonds, fenestrations, arches, scaffolding, formwork, timber/RCC/Steel frame construction, roof and roof covering questions

All Building construction techniques, methods and details: foundation, plinth, masonry, bonds, fenestrations, arches, scaffolding, formwork, timber/RCC/Steel frame construction, roof and roof covering questions →