GATE 2026 AR — Planning – Question 46

Project Management and Professional Practice · Construction project management techniques e.g. PERT, CPM · 2 marks · Numerical answer

A PERT project starts 27 July 2026. Activities and (optimistic, most likely, pessimistic) days are P 1→2(4, 6, 8), Q 1→3(5, 6, 13), R 2→5(6, 8, 22), S 2→3(8, 11, 14), T 3→5(2, 4, 12), U 3→4(4, 8, 18), V 4→5(5, 7, 15). All days are working except 15 August 2026. Give the completion date in August as an integer.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 30 to 30

Explanation

PERT means (a+4m+b)/6 are P 6, Q 7, R 10, S 11, T 5, U 9, V 8 days. Event 3 cannot occur until max(7, 6+11)=17; event 4 is 26; event 5 is max(6+10, 17+5, 26+8)=34. Thus critical path P–S–U–V takes 34 working days. Counting 27 July as day 1 gives 29 August before the holiday allowance. Excluding 15 August adds one day, so completion is 30 August.

More Construction project management techniques e.g. PERT, CPM questions

All Construction project management techniques e.g. PERT, CPM questions →