GATE 2025 AR — Planning – Question 30
Match P combined sewer, Q vacuum sewer, R partially separate system, S pressurised sewer with 1 roof rain joins sewage but other stormwater stays separate, 2 sewage and all stormwater together, 3 pumps residences into pressure sewer, 4 negative pressure draws sewage and air, 5 fully separate sewage/stormwater networks.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) P–2; Q–4; R–1; S–3
Explanation
Combined sewerage carries sewage with stormwater(2). Vacuum systems use negative pressure(4). A partially separate system admits specified roof/surface runoff to sewage while other stormwater stays separate(1). Pressure sewers use pumping(3). The matching sequence is 2, 4, 1, 3, A.