GATE 2025 AR — Planning – Question 29

Project Management and Professional Practice · Estimation, costing and specification · 2 marks · Multiple choice

Match P honeycomb brickwork, Q steel reinforcement, R brick-on-edge work, S excavation with 1 running metre, 2 cubic metre, 3 square metre, 4 kilogram, 5 number.

  1. P–1; Q–4; R–3; S–2
  2. P–3; Q–1; R–4; S–5
  3. P–5; Q–2; R–1; S–4
  4. P–3; Q–4; R–1; S–2

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (D) P–3; Q–4; R–1; S–2

Explanation

Honeycomb walling is measured by area(3), reinforcement by mass(4), the specified brick-on-edge linear work by length(1), and excavation by volume(2). Thus D. Measurement units describe the particular work item; brick-on-edge paving specified as an area would be a different item.

More Estimation, costing and specification questions