GATE 2023 AR — Planning – Question 12

Project Management and Professional Practice · Tendering · 1 mark · MTA

Which criterion is specifically mentioned in Special Conditions of Contract (SCC)?

  1. Scope and performance of the work
  2. Site mobilization advance
  3. Labour regulation
  4. Arbitration and law

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: MTA

Explanation

The final official key awards marks to all candidates (MTA); no single option is enforced. SCC contain project-specific additions or modifications to general conditions, and a site-mobilisation advance may be specified there. The precise allocation depends on the contract documents, so this item must retain its withdrawn/MTA grading.