GATE 2022 AR — Planning – Question 29

Project Management and Professional Practice · Construction planning and equipment · 2 marks · Multiple choice

Arrange construction-project stages under NBC 2016: P resource planning, Q project inception, R commissioning/handing over, S tendering, T site survey/soil investigation, U construction-methodology selection.

  1. P-Q-R-T-U-S
  2. T-Q-R-U-S-P
  3. Q-T-U-P-S-R
  4. Q-T-P-S-U-R

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (C) Q-T-U-P-S-R

Explanation

Begin with project inception, then establish site and soil information. Select the construction methodology, plan its resources, tender the work, and finally commission and hand it over. The order Q–T–U–P–S–R is C.