GATE 2022 AR — Planning – Question 29
Arrange construction-project stages under NBC 2016: P resource planning, Q project inception, R commissioning/handing over, S tendering, T site survey/soil investigation, U construction-methodology selection.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (C) Q-T-U-P-S-R
Explanation
Begin with project inception, then establish site and soil information. Select the construction methodology, plan its resources, tender the work, and finally commission and hand it over. The order Q–T–U–P–S–R is C.