GATE 2022 AR — Planning – Question 54
Which are public-private partnership models used for infrastructure projects?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (B) BOLT; (C) BOOT
Explanation
BOLT denotes Build–Own–Lease–Transfer and BOOT Build–Own–Operate–Transfer, recognised PPP structures. Select B, C. The other acronyms are not the models recognised in the source’s set. The allocation of ownership, operation and transfer obligations distinguishes the structures.