GATE 2019 AR – Question 59

Project Management and Professional Practice · Construction planning and equipment · 2 marks · Numerical answer

A power shovel excavates 1.8 m³ per batch. The average batch cycle time is 45 seconds, and lost time is 10 minutes per hour. Assume six working hours per day. The amount of soil excavated per day, in m³, is ___ (rounded off to two decimal places).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 719.75 to 720.25

Explanation