The operational status of an HEMM in a shift is shown in the diagram. The availability of
the machine in % is _____________________.

1T
2T
400
A
B
0
1
8
3
5
6
7.5
Breakdown state
Shift duration hours

Diagram for GATE 2018 MN question 25

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 56.0 to 56.5