GATE 2018 MN – Question 35

Mineral Economics, Mine Planning, Systems Engineering · 2 marks · Numerical answer

Economic feasibility of two methods is examined for meeting a targeted mine production.
On a yearly basis, the following cost parameters (Rs in crores) are applicable for these
methods.

Method 1 Method 2
Fixed cost
20
5
Variable cost
2X
X2
The annual rate of production, ‘X’ in million tonnes for which both the methods will yield
the same operating cost is ___________________.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 5.0 to 5.0

Explanation