GATE 2018 MN – Question 39
In a sublevel stope, 20 m high excavation is made with ring drilling in a 6 m wide orebody.
In an effective shift time of 6 hrs, three rings are blasted resulting in 9 m extraction length.
LHDs of 5.0 m3 bucket capacity and cycle time of 5 minutes are used for ore
transportation. The number of LHDs required for this operation is _________________.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 3.0 to 3.0
Explanation