GATE 2018 MN – Question 48

Mining Geology, Mine Development and Surveying · 2 marks · Numerical answer

In a level terrain, a vertical orebody of 20 m uniform width is worked by surface mining
method. The density of the ore is 2.5 tonne/m3. The ultimate pit has a depth of 60 m, width
of 20 m at pit bottom, and a pit slope of 45o. The overall stripping ratio for this condition in
m3/tonne is ____________________.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 1.2 to 1.2

Explanation

We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort