Arrange the following in the correct sequence of operations in an integrated steel plant:
i.
Basic Oxygen Furnace (BOF)
ii.
Blast Furnace (BF)
iii.
Ruhrstahl Heraeus Degassing Process (RH)
iv.
Ladle Furnace Process (LF)

  1. BOF→BF→LF→RH
  2. BF→LF→BOF→RH
  3. RH→LF→BF→BOF
  4. BF→BOF→LF→RH

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (D) BF→BOF→LF→RH

Explanation

We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort