The GATE Grind

GATE 2026 CH – Question 46

Plant Design and Economics · Depreciation, rate of return, payback period and discounted cash flow · 2 marks · Multiple choice

In a certain project, 15% of the total investment is the working capital. The minimum acceptable rate of return is 4.95% and the period of evaluation is 15 years. Which one of the following is the maximum acceptable project payback period (in years)?

  1. 5
  2. 8
  3. 12
  4. 15

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 8

Explanation

For a uniform annual return $A$ and total investment $I$, recover working capital $0.15I$ at year 15. Break-even present worth gives $A[1-(1.0495)^{-15}]/0.0495+0.15I(1.0495)^{-15}=I$. Thus the limiting payback $I/A$ is about 11.2 years. Of the offered periods 5, 8, 12 and 15 years, the largest that does not exceed this limit is 8 years (B). Rounding the limit up to 12 would admit an unacceptable project.

Official GATE 2026 answer key: https://gate2026.iitg.ac.in/doc/download/2026/Keys/CH_Keys.pdf

More Depreciation, rate of return, payback period and discounted cash flow questions

All Depreciation, rate of return, payback period and discounted cash flow questions →