GATE 2024 CE (CE2) – Question 60

Water and Waste Water Quality and Treatment · Primary, secondary and tertiary treatment, effluent standards · 2 marks · Numerical answer

A circular settling tank is to be designed for primary treatment of sewage at a flow rate of 10 million liters/day. Assume a detention period of 2.0 hours and surface loading rate of 40000 liters/m$^2$/day. The height (in meters) of the water column in the tank is _______________ (rounded off to 2 decimal places).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 3.31 to 3.35

Explanation

**1. Convert the flow and loading units.** Flow is $10^7$ L/day = 10000 m³/day. Surface loading is 40000 L/(m²·day) = 40 m³/(m²·day), giving area $A=10000/40=250$ m².

**2. Calculate volume from detention time.** Two hours is 2/24 day, so $V=Q\,t=10000(2/24)=833.3333$ m³.

**3. Divide volume by plan area.** Water depth is $H=V/A=833.3333/250=3.33333$ m. **Answer: 3.33 m.** Equivalently, H equals surface loading times detention time when both use the same time unit.