The GATE Grind

GATE 2022 CH – Question 61

Plant Design and Economics · Depreciation, rate of return, payback period and discounted cash flow · 2 marks · Numerical answer

Information for a proposed greenfield project is provided in the table. The discounted cash flow for the fourth year is Rs ________ crores (rounded off to one decimal place).

Fixed capital investment (excluding land)Rs 250 crores
Salvage valueRs 0
Yearly revenue from product salesRs 120 crores
Yearly manufacturing cost (excluding depreciation)Rs 30 crores
Interest rate10% compounded annually
Annual taxation rate30%
Depreciation methodDouble declining balance* over seven years
Plant start-up2 years after project initiation

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 53.23 to 53.77

Explanation

Operation starts 2 years after the project begins, so the fourth year of the project is the second year after start-up ($k = 2$). The depreciation is $d_1 = \frac{2}{7} \times 250 = 71.43$, which leaves a book value of 178.57, and $d_2 = \frac{2}{7} \times 178.57 = 51.02$. The cash flow before tax is $120 - 30 = 90$. The taxable income is $90 - 51.02 = 38.98$ and the tax is $0.3 \times 38.98 = 11.69$, so the after-tax cash flow is $90 - 11.69 = 78.31$ crores. Discounted to the start at 10% over 4 years: $\frac{78.31}{1.1^4} = 53.5$ crores.