GATE 2022 ME (ME1) – Question 21
In a linear programming problem, if a resource is not fully utilized, the shadow price of that resource is
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (C) zero
Explanation
The shadow price is the gain in the objective for one more unit of the resource. If part of the resource is left over (the constraint is not binding), another unit does not change the optimum, so the shadow price is zero.