GATE 2022 CE (CE1) – Question 64
The vehicle counts in six successive 10-minute intervals are 10,11,12,15,13,11. Find the peak-hour factor for 10-minute subintervals (one decimal).
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 0.79 to 0.81
Explanation
The hourly volume is $10+11+12+15+13+11=72$ vehicles. The peak 10-minute count is 15, equivalent to 90 vehicles/h.
For six subintervals per hour, $PHF=72/(6\times15)=\mathbf{0.8}$.