Which forecasting method needs the least historical data?

  1. Econometric forecasting
  2. Linear regression
  3. ARIMA
  4. Simple exponential smoothing

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (D) Simple exponential smoothing

Explanation

Simple exponential smoothing updates a single running forecast using the latest observation: $F_{t+1}=\alpha A_t+(1-\alpha)F_t$. It does not need the multiple variables or longer history used in the other listed models. **D**.