GATE Production Planning and Control: Forecasting models – Previous Year Questions
8 GATE previous year questions on Forecasting models (Production Planning and Control, Mechanical Engineering) with answers and explanations, from every paper.
8 questions worth 13 marks in all (3 1-mark, 5 2-mark). Asked between 2016 and 2026, so you can see how the topic has been tested over time.
- GATE 2016 ME (ME3) Q64 – The demand for a two-wheeler was 900 units and 1030 units in April 2015 and May 2015, respectively. The forecast for the month of April 2015 was 850…
- GATE 2018 ME (ME1) Q26 – Which forecasting method equally weights each of the m most recent observations?
- GATE 2019 ME (ME1) Q27 – Monthly demand is January 450, February 440, March 460, April 510, May 520, June 495, July 475 and August 560. Using a simple three-month moving…
- GATE 2020 ME (ME2) Q43 – Monthly forecasts for months 1, 2 and 3 are 32.00, 31.80 and 31.82 respectively; actual sales are 30.00, 32.00 and 30.00. Forecasts use exponential…
- GATE 2021 ME (ME2) Q53 – The demand and forecast of an item for five months are given in the table. Month April May June July August --- --- --- --- --- --- Demand 225 220 285…
- GATE 2022 ME (ME2) Q32 – An electric car manufacturer underestimated the January sales of car by 20 units, while the actual sales was 120 units. If the manufacturer uses…
- GATE 2025 ME Q37 – Considering the actual demand and the forecast for a product given in the table below, the mean forecast error and the mean absolute deviation,…
- GATE 2026 ME Q60 – The actual demand for castings in a factory is 500 units and 635 units for the months of January 2026 and February 2026, respectively. The forecasted…