GATE Construction Management: Types of construction projects, estimation and costing, analysis of rates – Previous Year Questions
7 GATE previous year questions on Types of construction projects, estimation and costing, analysis of rates (Construction Management, Civil Engineering) with answers and explanations, from every paper.
7 questions worth 12 marks in all (2 1-mark, 5 2-mark). Asked between 2017 and 2024, so you can see how the topic has been tested over time.
- GATE 2017 CE (CE2) Q43 – Consider: P. One-brick-thick walls are measured in square metres. Q. One-brick-thick walls are measured in cubic metres. R. No deduction in brickwork…
- GATE 2021 CE (CE2) Q53 – Equipment costs ₹160000, salvage value ₹10000 and estimated life 5 years. Find difference between book values at end of year 4 using straight-line and…
- GATE 2021 CE (CE1) Q16 – A contractor estimates direct and indirect project costs of ₹160000 and ₹20000. If markup is 10% of the bid price, the quoted price in rupees is
- GATE 2021 CE (CE1) Q40 – Past ratios of Y’s bid price to X’s cost are 1.02,1.04,1.06,1.10,1.12 with frequencies 6,12,3,6,3. Based on these 30 bids, X’s probability of beating…
- GATE 2024 CE (CE2) Q47 – The expression for computing the effective interest rate (i eff) using continuous compounding for a nominal interest rate of 5% is i eff = m (1 +…
- GATE 2024 CE (CE1) Q16 – Consider the statements P and Q. P: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase. Q: Client's…
- GATE 2024 CE (CE1) Q51 – The initial cost of an equipment is Rs. 1,00,000. Its salvage value at the end of accounting life of 5 years is Rs. 10,000. The difference in…