GATE Construction Management: Types of construction projects, estimation and costing, analysis of rates – Previous Year Questions

3 GATE previous year questions on Types of construction projects, estimation and costing, analysis of rates (Construction Management, Civil Engineering) with answers and explanations, from every paper.

  1. GATE 2024 CE (CE2) Q47 (2 marks, Numerical answer) – The expression for computing the effective interest rate (i eff) using continuous compounding for a nominal interest rate of 5% is i eff = m (1 +…
  2. GATE 2024 CE (CE1) Q16 (1 mark, Multiple choice) – Consider the statements P and Q. P: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase. Q: Client's…
  3. GATE 2024 CE (CE1) Q51 (2 marks, Numerical answer) – The initial cost of an equipment is Rs. 1,00,000. Its salvage value at the end of accounting life of 5 years is Rs. 10,000. The difference in…