GATE 2024 CE (CE1) – Question 16
Consider the statements P and Q.
P: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client's Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) Both P and Q are TRUE
Explanation
The preliminary estimate is prepared at the end of planning and design and is used for budgeting. The detailed estimate is prepared with the final design and is used as the baseline to control the cost during execution. Both statements are true.