The GATE Grind

GATE 2024 CE (CE1) – Question 17

Concrete Structures · Design and detailing of beams and slabs · 1 mark · Multiple choice

The following figure shows the arrangement of formwork for casting a cantilever RC beam.

The correct sequence of removing the Shores/Props is

Diagram for GATE 2024 CE (CE1) question 17
  1. S1→S2→S3→S4→S5
  2. S5→S4→S3→S2→S1
  3. S3→S2→S4→S1→S5
  4. S3→S4→S2→S5→S1

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) S5→S4→S3→S2→S1

Explanation

A cantilever carries its load by hogging moment, with the largest moment at the support. The props are therefore removed starting from the free end and moving towards the support, so that the beam takes up its load gradually as a cantilever. The sequence is S5, S4, S3, S2, S1. (For a simply supported beam the props are removed from the middle towards the supports.)

More Design and detailing of beams and slabs questions

All Design and detailing of beams and slabs questions →