GATE 2026 AG – Question 62

Soil and Water Conservation Engineering · Soil and Water Erosion · 2 marks · Numerical answer

Bench terraces are planned on a 15% hill slope. Vertical interval is 2.5 m, riser slope is 1H:1V, and cut equals fill. Find earthwork volume in $\mathrm{m^3/ha}$,rounded to the nearest integer.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 2655 to 2658

Explanation

Write natural slope fraction $S=.15$ and vertical interval $V=2.5$ m. Total horizontal interval is $H=V/S=16.6667$ m. The riser occupies $V=2.5$ m horizontally, so bench width is $W=H-V=14.1667$ m. For a balanced level bench, the cut section is $A_c=VW/8=4.42708$ m². Terrace length per hectare is $10000/H=600$ m. Earth moved is the cut volume, not cut plus the same fill:$600(4.42708)=2656.25$ m³/ha, rounded **2656**.