- GATE 2021 AG Q18 – Approximately, how does sediment delivery ratio SDR vary with drainage area A?
- GATE 2021 AG Q42 – Bench terraces are planned on10% land slope, vertical interval2.5 m, batter slope100%. Find working width(m) and cultivated-area loss(%).
- GATE 2021 AG Q58 – A windbreak is 15 m high and 200 m long. Threshold wind speed at 15 m height is 9.6 m/s;5-year design wind16 m/s, deviating20° from normal to the…
- GATE 2022 AG Q30 – In the USLE slope-length relation, the stated exponent is .5 (the source calls this the soil-loss ratio). Slope length from the divide is 600 m,…
- GATE 2022 AG Q42 – Design a parabolic grass waterway for 2.85 m³/s on3% slope. Permissible velocity1.78 m/s and Manning n=.04. Excluding freeboard, select top width and…
- GATE 2024 AG Q18 – Which process transports the largest portion of soil in typical wind erosion?
- GATE 2024 AG Q19 – Which bench terraces suit hilly regions with heavy rain where a major fraction must be safely drained as runoff?
- GATE 2024 AG Q31 – An area of 6% slope has its slope length halved with all other factors unchanged. Find the percentage reduction in annual soil loss, to two decimals.
- GATE 2024 AG Q59 – Contour bunds on a 3% slope in a semiarid region are spaced30 m horizontally. The10-year daily maximum effective rainfall is 20 cm. Find design…
- GATE 2025 AG Q49 – Windbreaks 2.7 m high protect a wheat field. Wind perpendicular to the barrier is 9 m/s at 15 m height; the minimum 15 m wind speed that moves the…
- GATE 2026 AG Q22 – In the wind-erosion relation used here, how does the transported soil amount vary?
- GATE 2026 AG Q23 – A chute spillway’s discharge-carrier bed changes from a steeper slope to a milder slope. Which transition is provided?
- GATE 2026 AG Q62 – Bench terraces are planned on a 15% hill slope. Vertical interval is 2.5 m, riser slope is 1H:1V, and cut equals fill. Find earthwork volume in…