GATE 2011 CS (CS1) – Question 9

General Aptitude · Quantitative Aptitude: Algebra, Geometry and Mensuration · 2 marks · Multiple choice

A transporter receives the same daily orders and has an initial backlog. Seven trucks clear all orders by the end of day four; three trucks clear them by the end of day ten. Find the minimum trucks to eliminate pending orders by the end of day five.

  1. 4
  2. 5
  3. 6
  4. 7

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (C) 6

Explanation

Measure work in truck-days. If backlog is B and daily arrivals r, B+4r=28 and B+10r=30. Thus r=1/3 and B=80/3. For five days, 5t≥B+5r=85/3, so t≥17/3≈5.667. Six trucks are required, C.