A worker notices that the hour hand of the factory clock moved 225° during her stay. How long did she stay?

  1. 3.75 hours
  2. 4 hours and 15 minutes
  3. 8.5 hours
  4. 7.5 hours

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (D) 7.5 hours

Explanation

The hour hand completes 360° in 12 hours, so its speed is 30° per hour. The elapsed time is 225/30=7.5 hours. Choose D; using the minute-hand speed would measure a different interval.