GATE 2020 PI – Question 8
52 workers can complete a highway strip in10 days.12 are sent elsewhere before the work begins. With unchanged individual productivity, how many extra days are needed?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) 3
Explanation
The work is52×10=520 worker-days. With40 workers it takes520/40=13 days. Extra time is13−10=3 days, A. The question requests additional days, not the new total duration.