The GATE Grind

GATE 2023 MN – Question 22

Mineral Economics, Mine Planning, Systems Engineering · Systems Engineering · 1 mark · Multiple choice

Which statement about classical project scheduling techniques is correct?

  1. Both CPM and PERT are deterministic.
  2. Both CPM and PERT are probabilistic.
  3. CPM is deterministic and PERT is probabilistic.
  4. CPM is probabilistic and PERT is deterministic.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (C) CPM is deterministic and PERT is probabilistic.

Explanation

Classical CPM assigns a single deterministic duration to each activity. Classical PERT uses optimistic, most likely and pessimistic durations to estimate uncertain completion times. Therefore C. This distinction concerns the conventional models used in the question.

More Systems Engineering questions

All Systems Engineering questions →